Montauk Point

General

USACE District:New YorkCongressional Dist.:1
Type:Shore Protection Project Length:0.2 miles
State:NY
Non-Structural:unknown
Structural:OTHER
Ecosystem Restoration:No
Beneficial Use:No
Feasibility:No
Coastal Location:South Shore of Long Island and Staten Island

Project Reliability

The reliability was updated on: 11/3/2011 11:25:



Unconstructed

Activities

Date of Next Renourishment:data unavailable
Date of Last Renourishment:data unavailable
Desired Renourishment Cycle (yrs):data unavailable
# of Nourishment Operations:data unavailable
Is Erosion Partially Induced by Navigation?No
Project Phase:Pre-construction engineering and design
Notes: